25 St George Street

London W1

Architect/Designer:
Hamilton Associates
Client:
Mayfair Ltd
Main Contractor:
Galliford Try
Portland Stone:
Bowers Basebed
Scope of Project:
Stone-on-precast Cladding

The project at 25 St George Street involved the construction of an office and residential development in the heart of London'€™s West End.

From the early stages of the project Albion Stone'€™s Bowers Basebed was specified for the development. Galliford Try told Albion that the main façade was designed as stone-on-precast with the rear elevation still under discussion.

Albion Stone supplied raw Basebed blocks supplied directly to sub-contractor of the project, Stirling Services. The Portland Stone was incorporated into Stirling Services'€™ panels at their factory, then fixed by them on site. The total value of the contract for this project was £500,000.